Updated Requirement as per 22nd Nov:
[VK]
Hi Team,
As discussed, we would like to convert the “To be Reviewed in next Qtr.” dropdown in DMA to “Delay Reason”. Please find the below snip for reference. Also, see the below bullets for the updated dropdown list.
Delay Reason –
Missing Requirements
Not Prioritized
Bandwidth Issue
Requirement as per the discussion on 14th Sept:
The TSM wants to identify the individual who is working on a particular demand. Currently, PdM, SA and TSMs have tasks created who can work on the demand parallelly.
Stages |
Task Owner |
Submitted |
PdM |
SA | |
Screening |
PdM |
SA | |
TSM | |
Qualify |
TSM |
SA | |
PdM |
The TSM wants to identify how much time the individual (Task owner) who is working on a particular demand is taking.
The TSM wants to identify the reason for which the task owner is taking time. Therefore, he/she wants to log the delay reason.
All of this above information should be available in a consolidated way so that the TSM can identify all the ongoing tasks of ongoing SPR demands.
Earlier by Khizar
It should come in SPR section just below the Delay option.
The dropdown of the delay reason and delay owner should be specific to the demand stages. Please refer to the attached file.
The idea has been updated as per the new ask.
UP to date requirement has been added in the description section. Robin to work on the solution. Also, we need to decide if such a requirement will be implemented in CT DMA or not.